Electrum signs contract with Polish Energy Partners

Electrum (Consortium Leader) and Power Network Construction Company MEGA-POL S.A. Consortium will perform complex construction and electrical power engineering works, establishing high- and medium voltage transformer stations, power lines, communication, as well as cable medium voltage and fiber optic networks, for the execution of Rajgród and Gawłowice wind farms.

Gawłowice Wind Farm, with total capacity of 41,4 Megawatts, will be built within the municipality of Radzyń Chełmiński in Kuyavian Voivodeship and will consist of 18 turbines with a unit capacity of 2,3 Megawatts.

Rajgród Wind Farm, with total capacity of 25,3 Megawatts, consisting of 11 windpower plants with capacity of 2,3 Megawatts each, will be located within the municipality of Grajewo in Podlaskie Voivodeship.

Turbines for both investments will be provided by Siemens.