Energizing WF Zaporozhye in Ukraine

The end of the year was extremely intense for the whole Electrum team. And fortunately it brings good news. Yesterday we energized Zaporizhia Wind Park! The transmitting line, which is over 23 km long, has successfully passed 24-hour tests of applying a voltage of 330 kV.
As a result, we were able to carry out busbar tests and, most importantly, to start up the 330 kV transformer for the first time. It was the best way to celebrate Power Engineer’s Day, a holiday that in Ukraine falls on December 22.

Thanks to the commitment of the entire Electrum UA team and our business partners Eurocape New Energy and subcontractors Structum, Synergia, EDS-ENGINEERING we managed to successfully complete the project.