Further 28 turbines, along with the necessary infrastructure, will be built in the next stage of Banie Wind Farm construction. Like in a previous stage of the project, Electrum is a General Contractor responsible for complex execution of electrical works.
The first part of the project consisted of 25 turbines with a total capacity of 50 MW and was successfully completed in December 2015, after only 5 months since beginning of the works. Within a consortium created with PBDI S.A. to implement infrastructure for the needs od Banie Wind farm, Electrum’s scope of work included execution of the 110/33 kV and 220/110 kV substations along with 220 kV cable line.