Wielkopolska Wind Farm – 79 MW
For the 79 MW Wielkopolska Wind Farm, we carried out comprehensive construction works, including the installation of 12.9 km of 110 kV HV cable lines and a fiber optic route connecting PSE Kromolice and the Wielkopolska GPO. Our team developed the detailed design documentation, obtained all necessary permits, and delivered key infrastructure equipment. Electrum’s scope of work also included laying, connecting, and testing the cable line and fiber optic route, as well as preparing the full documentation required to commission the facility.