Dębsk Wind Farm – 121 MW
The Dębsk Wind Farm, with an impressive capacity of 121 MW, is one of the largest wind projects in Poland, located in the Żuromin and Kuczbork-Osada municipalities in the Masovian Voivodeship. Electrum, as a key partner, was responsible for the construction of the longest 110 kV high-voltage cable line in Europe, stretching 62 kilometers, as well as comprehensive electrical works and the construction of the 110/30 kV GPO Dębsk substation. The project also included a medium-voltage cable line exceeding 85 kilometers in length, equipped with modern fiber optic cables and grounding systems.
The wind farm produces approximately 366 GWh of energy annually—enough to power 183,000 households—while significantly reducing CO₂ emissions by as much as 318,000 tons per year. The project also contributed to the modernization of the local energy infrastructure, ensuring a reliable connection to the national transmission grid.