Krzywińskie Solar Farm – 20 MW
As the EPC general contractor, Electrum was responsible for the comprehensive implementation of the Krzywińskie PV project: from obtaining building permits to the occupancy permit and generation license.
As part of the execution works, we prepared, among others, an analysis of reactive power compensation and control based on PV inverters, as well as a technical concept for power evacuation – including the selection of MV line technology, GPO, and HV line. We also acquired the property for the GPO, the right to properties for MV and HV connection lines with a total length of 15.0 km, and obtained a generation license promise for electricity production.
To meet the NC RFG grid code requirements, Electrum’s proprietary solutions were installed at the Krzywińskie farm – Renedium, an active and reactive power controller, and the EMACS System for energy facility monitoring and control.